A NEW 19.5km water pipeline is helping to manage resources across Essex during one of the driest summers on record.

Essex and Suffolk Water’s new pipeline supports supplies for around 370,000 customers.

Construction started on the pipeline in 2023 and was completed earlier this year.

The pipeline connects raw water supplies in the Layer-de-la-Haye and Langford areas near Maldon and has already helped to protect customers’ supplies during the long, hot, dry summer.

It has the capacity to carry up to 50 million litres of raw water a day to treatment facilities in Langford.

The pipeline uses gravity to drive most of the water’s flow, reducing the need for pumps and minimising ongoing energy costs and carbon consumption.

The route was designed to avoid ecologically important areas, such as the Abberton Reservoir, a designated Site of Special Scientific Interest (SSSI).

As well as reinstating the working area, the team installed 4km of new hedgerow was added to increase biodiversity along the route.

The pipeline crosses 19 roads and required cooperation with many landowners.

Company engineers worked with specialists to drill beneath the River Blackwater and the Langford Cut, passing the pipes through a tunnel under the two watercourses to avoid any impact on these areas.

The project was a joint effort with partners including Aquazone, Complete Moling Services and design company Stantec.

Daniel Wilson, Essex and Suffolk Water’s project manager, said: "The new pipeline connects raw water supplies across Essex, protecting customers’ supplies and the environment by adding flexibility to how we draw upon the area’s resources.

"This has been quite an exciting project to work on, because of the great potential it has to support around 370,000 customers.

"Mindful of both our duties to protect the environment and to invest customers’ money efficiently, we faced those challenges head-on and have created a pipeline that delivers on our operational needs, our regulatory obligations, as well as those important commitments.

"While the pipeline has largely been constructed in rural land, where we have now completed reinstatement work to restore the working areas, the project has involved crossing 19 roads and working with many landowners.

"We would like to take this opportunity to thank everyone who we have worked with, or who has been impacted by the work, for their patience and support."

The savings made on this project will be used to further invest in the region’s infrastructure.